Phase 1 - Road Reconstruction June 3 - July 7, 2023

6.24.23: The major reconstruction is complete. Starting next week, the road will be striped. The following week, utility adjustments will be made and the project will be complete. Thank you for your patience throughout this project. 

Vendors

Prior Updates from the Owners Association

Frequently Asked Questions

Scope of Project

The SMOA is working with MR Tanner, and Frank Civil Consulting on the first phase of road reconstruction in Superstition Mountain. 

This work will cover Superstition Mountain Drive (from the gatehouse to just past the entrance to Juniper Village) and major portions of the roads in Juniper and Sycamore Villages, as highlighted on the map below.

Superstition_Mountain_-_Sequencing_Map

Road Reconstruction Activity & Photos

Milling Work - June 7-9, 2023